Planning and Engineering 90
This department's accounts sit in 6 funds (001, 006, 202, 207, 311, 900); the figures below cover all funds in scope. These figures cover expenditure accounts only. Revenue, asset and liability accounts are excluded, so a department's budget here is not its total fund activity.
- Revised budget$19,277,529.574,704 accounts · 471 accounts with a budget line
- Spent$19,077,810.22Posted ledger expenditure to the cutoff
- Committed$1,296,716.91Encumbrances $1,296,716.91 · requisitions $0.00
- Available$1,128,370.695.9% of the budget
$2,177,239.07 posted with no positive budget line. Availability is measured only over accounts with a positive revised budget, so the accounts carrying this spending contribute nothing to the available figure above — neither the $2,177,239.07 posted to them nor the commitments recorded against them. That is why revised − spent − committed is not the available figure: the two differ by $2,225,368.25, which is the whole activity on those accounts — this spending, those commitments, and their own zero-or-negative budget lines. The figures themselves are unchanged; the difference is the rule, not an error.
Fiscal year 2024: 2024-01-01 to 2024-12-31 — the year is closed. How these figures are defined
| Account | Description | Fund | Revised budget, not sorted | Spent, not sorted | Available, not sorted | Committed, not sorted | Percent used, not sorted | Status |
|---|---|---|---|---|---|---|---|---|
| 202-3-00-90-910-0000-00-110-486915- | Const Exp · Contracted Construction | Capital Improvements Fund | $4,994,843.96 | $7,292,074.29 | -$2,308,137.33 | $10,907.00 | 146.0% | |
| 202-3-00-90-910-0000-00-140-486915- | Const Exp · Contracted Construction | Capital Improvements Fund | $690,000.00 | $2,002,806.04 | -$1,312,806.04 | $0.00 | 290.3% | |
| 001-3-00-90-100-0000-00-000-416201- | FT Wages · Administration | General Fund | $1,590,524.04 | $1,278,461.50 | $312,062.54 | $0.00 | 80.4% | |
| 202-3-00-90-940-0000-00-100-486919- | Proj Plnng · System Planning | Capital Improvements Fund | $707,804.08 | $736,398.84 | -$139,073.33 | $110,478.57 | 104.0% | |
| 006-3-00-90-100-0000-00-000-486915- | Const Exp · Administration | Enhancement Operating Fund | $0.00 | $571,030.52 | Not applicable | $0.00 | Not applicable | |
| 001-3-00-90-100-0000-00-000-426301- | Ret Contri · Administration | General Fund | $574,419.00 | $509,301.60 | $65,117.40 | $0.00 | 88.7% | |
| 006-3-00-90-940-0000-00-100-486919- | Proj Plnng · System Planning | Enhancement Operating Fund | $602,674.49 | $460,607.81 | $142,066.68 | $0.00 | 76.4% | |
| 202-3-00-90-910-0000-00-132-486915- | Const Exp · Contracted Construction | Capital Improvements Fund | $400,000.00 | $403,940.55 | -$3,940.55 | $0.00 | 101.0% | |
| 202-3-00-90-100-0000-00-000-416201- | FT Wages · Administration | Capital Improvements Fund | $0.00 | $393,650.63 | Not applicable | $0.00 | Not applicable | |
| 006-3-00-90-910-0000-00-133-486919- | Proj Plnng · Contracted Construction | Enhancement Operating Fund | $377,805.00 | $376,743.30 | $1,061.70 | $0.00 | 99.7% | |
| 202-3-00-90-100-0000-00-000-527301- | Ad Val Fee · Administration | Capital Improvements Fund | $448,326.96 | $345,707.12 | $102,619.84 | $0.00 | 77.1% | |
| 006-3-00-90-910-0000-00-131-486915- | Const Exp · Contracted Construction | Enhancement Operating Fund | $379,626.00 | $341,562.63 | $38,063.37 | $0.00 | 90.0% | |
| 202-3-00-90-910-0000-00-110-486919- | Proj Plnng · Contracted Construction | Capital Improvements Fund | $85,000.00 | $300,402.07 | -$215,402.07 | $0.00 | 353.4% | |
| 006-3-00-90-910-0000-00-110-486919- | Proj Plnng · Contracted Construction | Enhancement Operating Fund | $415,995.00 | $254,995.96 | $160,999.04 | $0.00 | 61.3% | |
| 202-3-00-90-940-0000-00-100-517220- | Pro Srvc · System Planning | Capital Improvements Fund | $152,558.00 | $252,807.00 | -$100,249.00 | $0.00 | 165.7% | |
| 001-3-00-90-100-0000-00-000-426302- | Med Ins · Administration | General Fund | $199,792.20 | $194,986.67 | $4,805.53 | $0.00 | 97.6% | |
| 202-3-10-90-910-0606-00-000-486915- | Const Exp · Contracted Construction | Capital Improvements Fund | $0.00 | $188,841.00 | Not applicable | $0.00 | Not applicable | |
| 202-3-10-90-910-0708-00-000-486915- | Cnstrc Exp · Contracted Construction | Capital Improvements Fund | $179,047.60 | $161,046.25 | $0.00 | $18,001.35 | 89.9% | |
| 202-3-00-90-910-0000-00-131-486919- | Proj Plnng · Contracted Construction | Capital Improvements Fund | $2,000.00 | $142,992.16 | -$145,502.16 | $4,510.00 | 7149.6% | |
| 202-3-83-90-920-0210-00-000-416211- | Seasonal · Capital Construction-In House | Capital Improvements Fund | $0.00 | $137,882.02 | Not applicable | $0.00 | Not applicable | |
| 006-3-00-90-910-0000-00-122-486919- | Proj Plnng · Contracted Construction | Enhancement Operating Fund | $130,000.00 | $109,800.00 | $20,200.00 | $0.00 | 84.5% | |
| 202-3-00-90-920-0000-00-110-486912- | Const Mat · Capital Construction-In House | Capital Improvements Fund | $100,000.00 | $104,808.35 | -$15,884.78 | $11,076.43 | 104.8% | |
| 202-3-00-90-100-0000-00-000-426301- | Ret Contri · Administration | Capital Improvements Fund | $199,992.00 | $104,806.04 | $95,185.96 | $0.00 | 52.4% | |
| 001-3-00-90-100-0000-00-000-517224- | Sft Contrc · Administration | General Fund | $121,884.24 | $101,642.40 | $20,241.84 | $0.00 | 83.4% | |
| 202-3-00-90-100-0000-00-000-416211- | Union Wage · Administration | Capital Improvements Fund | $499,992.00 | $90,999.69 | $408,992.31 | $0.00 | 18.2% | |
| 202-3-00-90-920-0000-00-122-486912- | Const Mat · Capital Construction-In House | Capital Improvements Fund | $227,100.00 | $89,452.60 | $136,848.06 | $799.34 | 39.4% | |
| 202-3-10-90-920-0809-00-000-416201- | FT Wages · Capital Construction-In House | Capital Improvements Fund | $0.00 | $86,302.86 | Not applicable | $0.00 | Not applicable | |
| 202-3-83-90-920-0210-00-000-416201- | FT Wages · Capital Construction-In House | Capital Improvements Fund | $0.00 | $84,281.58 | Not applicable | $0.00 | Not applicable | |
| 202-3-00-90-910-0000-00-122-486915- | Const Exp · Contracted Construction | Capital Improvements Fund | $332,425.96 | $83,234.05 | $249,191.91 | $0.00 | 25.0% | |
| 202-3-84-90-910-1201-00-000-486919- | Proj Plnng · Contracted Construction | Capital Improvements Fund | $90,239.37 | $76,645.42 | $13,593.95 | $0.00 | 84.9% | |
| 202-3-00-90-920-0000-00-122-486915- | Const Exp · Capital Construction-In House | Capital Improvements Fund | $402,000.04 | $73,047.08 | $322,055.05 | $6,897.91 | 18.2% | |
| 202-3-00-90-910-1401-00-000-486919- | Proj Plnng · Contracted Construction | Capital Improvements Fund | $197,204.66 | $71,508.85 | -$18,180.52 | $143,876.33 | 36.3% | |
| 202-3-00-90-100-0000-00-000-426302- | Med Ins · Administration | Capital Improvements Fund | $0.00 | $69,085.11 | Not applicable | $0.00 | Not applicable | |
| 202-3-10-90-920-1101-00-000-416201- | FT Wages · Capital Construction-In House | Capital Improvements Fund | $0.00 | $61,298.45 | Not applicable | $0.00 | Not applicable | |
| 202-3-10-90-910-1101-00-000-486915- | Cnstrc Exp · Contracted Construction | Capital Improvements Fund | $3,061.17 | $59,463.51 | -$56,402.34 | $0.00 | 1942.5% | |
| 001-3-00-90-930-0000-00-000-517221- | Ind Cntrc · Natural Resource Management | General Fund | $51,575.04 | $53,865.00 | -$2,289.96 | $0.00 | 104.4% | |
| 202-3-10-90-910-1009-00-000-486915- | Const Exp · Contracted Construction | Capital Improvements Fund | $48,214.33 | $48,214.33 | $0.00 | $0.00 | 100.0% | |
| 202-3-00-90-100-0000-00-000-466704- | Gas & Oil · Administration | Capital Improvements Fund | $65,000.04 | $47,002.14 | $17,906.26 | $91.64 | 72.3% | |
| 202-3-10-90-920-1012-00-000-416201- | FT Wages · Capital Construction-In House | Capital Improvements Fund | $0.00 | $46,415.20 | Not applicable | $0.00 | Not applicable | |
| 202-3-30-90-920-0410-00-000-486915- | Const Exp · Capital Construction-In House | Capital Improvements Fund | $39,099.75 | $39,099.75 | $0.00 | $0.00 | 100.0% | |
| 202-3-50-90-910-0306-00-000-486919- | Proj Plnng · Contracted Construction | Capital Improvements Fund | $0.00 | $38,240.30 | Not applicable | $16,759.70 | Not applicable | |
| 202-3-10-90-910-1012-00-000-486915- | Cnstrc Exp · Contracted Construction | Capital Improvements Fund | $1.00 | $36,110.00 | -$36,109.00 | $0.00 | 3611000.0% | |
| 202-3-00-90-920-1400-00-000-416201- | FT Wages · Capital Construction-In House | Capital Improvements Fund | $0.00 | $36,032.04 | Not applicable | $0.00 | Not applicable | |
| 202-3-00-90-100-0000-00-000-527310- | Oper Resv · Administration | Capital Improvements Fund | $29,913.79 | $34,180.98 | -$4,267.19 | $0.00 | 114.3% | |
| 202-3-00-90-910-0000-00-132-486919- | Proj Plnng · Contracted Construction | Capital Improvements Fund | $150,000.00 | $33,908.88 | $116,091.12 | $0.00 | 22.6% | |
| 202-3-00-90-920-1401-00-000-416201- | FT Wages · Capital Construction-In House | Capital Improvements Fund | $0.00 | $32,876.31 | Not applicable | $0.00 | Not applicable | |
| 006-3-00-90-910-0000-00-122-486915- | Const Exp · Contracted Construction | Enhancement Operating Fund | $33,000.00 | $32,750.00 | $250.00 | $0.00 | 99.2% | |
| 202-3-00-90-910-0000-00-140-486919- | Proj Plnng · Contracted Construction | Capital Improvements Fund | $0.00 | $27,208.24 | Not applicable | $576.23 | Not applicable | |
| 202-3-83-90-920-0210-00-000-426301- | Ret Contri · Capital Construction-In House | Capital Improvements Fund | $0.00 | $26,704.87 | Not applicable | $0.00 | Not applicable | |
| 001-3-00-90-100-0000-00-000-517201- | Advertisng · Administration | General Fund | $38,000.04 | $26,467.63 | $5,599.92 | $5,932.49 | 69.7% | |
| Total over all matching accounts | $19,277,529.57 | $19,077,810.22 | $1,128,370.69 | $1,296,716.91 | 99.0% | |||
How to read these figures
- These figures cover expenditure accounts only. Revenue, asset and liability accounts are excluded, so a department's budget here is not its total fund activity.
- Spent is posted general-ledger expenditure for the fiscal year to the publication cutoff — not payments, and not commitments. Committed is encumbrances plus requisitions: money ordered or requested but not yet paid. The two are never added together into a single “spending” figure.
- Available follows the portal's existing rule: an account with a zero or negative revised budget contributes no availability, and shows “Not applicable”. Where spending was still posted against such an account, the amount is stated above rather than left out of the arithmetic.
- Figures come from publication #2637. Munis is the accounting system of record; nothing on this page is a working or unpublished figure.