Recreation and Park Commission of East Baton Rouge ParishVisit BREC.org
BRECFiscalTransparency Portal

Making EBR better.

Budget and actuals

Start at the fiscal year and drill down to a single general-ledger account and its posted entries. Figures at each level are SQL totals over every account beneath it, so a parent row always equals the sum of its children rather than only the rows shown. This browser covers expenditure accounts; revenue, asset and liability accounts are not summed into these budget and actual figures, and revenue appears on the home revenue figures instead.

Filter these figures

The filters above are for the flat account list. The drilldown table on this page narrows by clicking a row, and the URL always shows exactly where you are.

Divisions within Enhancement Operating Fund

Divisions within Enhancement Operating Fund: revised budget and expenditure

Which divisions hold the budget, and how much of it has been spent?

See every figure in “Divisions within Enhancement Operating Fund: revised budget and expenditure” as a table
Divisions within Enhancement Operating Fund: revised budget and expenditure: 8 categories, 2 measures. Source: Publication #2618, data through 2026-11-17. Revised budget is the sum of this group's account-level revised budgets..
DivisionRevised budgetExpenditureOpen
80 — Park Operations$7,201,945.00$7,612,892.98Open
25 — General Recreation$3,934,356.45$1,045,981.47Open
90 — Planning and Engineering$3,444,012.54$1,740,714.56Open
21 — Golf$14,513.89$203,342.93Open
13 — Finance$66,000.00$145,600.00Open
29 — Zoo$0.00$47,308.62Open
00 — No Department$0.00$941.32Open
17 — Information Technology$0.00$0.00Open

Nodes: 8 · Accounts: 121 · Entry Count: 5,915

Publication #2618, data through 2026-11-17. Revised budget is the sum of this group's account-level revised budgets.How this figure is computed

Divisions in fiscal year 2025, ranked by budget size. Totals below are over all 8 items at this level.
DivisionOriginal budgetRevised budgetExpenditureUtilisationAvailableAccountsEntriesNext level
80 — Park Operations$6,550,000.00$7,201,945.00$7,612,892.98105.7%-$1,444,560.6659 accounts4,857 entrysDrill down
25 — General Recreation$3,905,344.00$3,934,356.45$1,045,981.4726.6%$2,611,561.7823 accounts843 entrysDrill down
90 — Planning and Engineering$3,300,000.00$3,444,012.54$1,740,714.5650.5%$1,586,627.3420 accounts142 entrysDrill down
21 — Golf$0.00$14,513.89$203,342.931401.0%-$188,923.315 accounts18 entrysDrill down
13 — Finance$0.00$66,000.00$145,600.00220.6%-$79,600.002 accounts12 entrysDrill down
29 — Zoo$0.00$0.00$47,308.62Not applicableNot applicable11 accounts40 entrysDrill down
00 — No Department$0.00$0.00$941.32Not applicableNot applicable1 account3 entrysDrill down
17 — Information Technology$0.00$0.00$0.00Not applicableNot applicable0 accounts0 entrysDrill down
Total at this level$13,755,344.00$14,660,827.88$10,796,781.8873.6%$2,431,562.25121 accounts5,915 entrys

How to read these figures

  • Utilisation is expenditure ÷ revised budget, shown only when the revised budget is greater than zero. A zero or negative budget is labelled, never shown as a percentage.
  • Available = revised − expenditure − encumbrance − requisition reservations.
  • A parent figure covers every account beneath it, including ones not shown because the list is capped; the row counts state the population. Revised budget at every level is the sum of the revised budgets of the accounts inside it (per-account sum).
  • Unassigned means the ledger code is blank in that segment for the accounts concerned — it is a real grouping, not an error to be summed away.