General-ledger accounts
Every published account for fiscal year 2026, with its budget and posted activity. Totals are computed by the database over the whole filtered selection and do not change when the page size changes.
- Revised budget$3,185,500.0016 accounts with a budget line, 284 accounts without one
- Expenditure$1,363,630.23105 ledger entrys across 14 accounts
- Open commitments$1,639,502.36$1,639,502.36 encumbered · $0.00 requisitioned
- Prior year (2025)$5,216,547.45Same accounts, previous fiscal year
Which accounts explain most of the spending?
See every figure in “Where the money went: the largest accounts by expenditure” as a table
| Account | Expenditure | Revised budget | Open |
|---|---|---|---|
| 202-3-00-90-910-0000-00-110-486919- — Proj Plnng | $482,477.22 | $1,360,000.00 | Open |
| 202-3-00-90-910-0000-00-133-486919- — Proj Plnng | $372,329.84 | $10,000.00 | Open |
| 202-3-00-90-910-0000-00-140-486919- — Proj Plnng | $202,703.19 | $800,000.00 | Open |
| 202-3-00-90-910-0000-00-122-486919- — Proj Plnng | $179,452.75 | $400,000.00 | Open |
| 202-3-00-90-910-0000-00-131-486919- — Proj Plnng | $82,926.38 | $300,000.00 | Open |
| 202-3-00-90-910-0000-00-134-486919- — Proj Plnng | $24,305.00 | $230,000.00 | Open |
| 202-3-83-90-910-0109-00-000-486919- — Proj Plnng | $6,321.04 | $0.00 | Open |
| 202-3-00-90-910-0000-00-100-486919- — Proj Plnng | $6,081.25 | $0.00 | Open |
| 006-3-00-90-910-0000-00-110-486919- — Proj Plnng | $3,372.28 | $0.00 | Open |
| 202-3-00-90-940-0000-00-100-486919- — Proj Plnng | $1,950.76 | $19,000.00 | Open |
| 202-3-00-90-920-0000-00-122-486919- — Proj Plnng | $1,012.06 | $5,000.00 | Open |
| 006-3-00-90-910-0000-00-133-486919- — Proj Plnng | $493.41 | $0.00 | Open |
| All other matching accounts | $205.05 | No data | Open |
Accounts: 300 · Entry Count: 105
Publication #2741, data through 2026-11-18.How this figure is computed
Is spending concentrated in accounts that used little of their budget, or in accounts that exceeded it?
See every figure in “How much of their revised budget each account has used” as a table
| Share of revised budget used | Accounts | Expenditure in these accounts | Open |
|---|---|---|---|
| Up to 25% | 5 | $27,267.82 | Open |
| 26–50% | 4 | $947,559.54 | Open |
| 51–75% | 0 | $0.00 | Open |
| 76–100% | 0 | $0.00 | Open |
| Over 100% | 1 | $372,329.84 | Open |
| No published budget | 284 | $0.00 | Open |
| Revised budget is zero or negative | 6 | $16,473.03 | Open |
| Revenue account — not an expenditure measure | 0 | $0.00 | Open |
Accounts: 300
Publication #2741, data through 2026-11-18.How this figure is computed
Which accounts still have budget left, and which have already exceeded it?
See every figure in “Remaining budget, including accounts that have gone past theirs” as a table
| Account | Available | Open |
|---|---|---|
| 202-3-00-90-910-0000-00-110-486919- — Proj Plnng | -$108,695.13 | Open |
| 202-3-00-90-910-0000-00-133-486919- — Proj Plnng | -$434,746.24 | Open |
| 202-3-00-90-910-0000-00-140-486919- — Proj Plnng | $203,593.16 | Open |
| 202-3-00-90-910-0000-00-122-486919- — Proj Plnng | $195,537.25 | Open |
| 202-3-00-90-910-0000-00-131-486919- — Proj Plnng | $146,847.10 | Open |
| 202-3-00-90-910-0000-00-134-486919- — Proj Plnng | $174,101.00 | Open |
| 202-3-83-90-910-0109-00-000-486919- — Proj Plnng | Revised budget is zero, negative, or not published, so availability is undefined | Open |
| 202-3-00-90-910-0000-00-100-486919- — Proj Plnng | Revised budget is zero, negative, or not published, so availability is undefined | Open |
| 006-3-00-90-910-0000-00-110-486919- — Proj Plnng | Revised budget is zero, negative, or not published, so availability is undefined | Open |
| 202-3-00-90-940-0000-00-100-486919- — Proj Plnng | $17,049.24 | Open |
| 202-3-00-90-920-0000-00-122-486919- — Proj Plnng | $3,987.94 | Open |
| 006-3-00-90-910-0000-00-133-486919- — Proj Plnng | Revised budget is zero, negative, or not published, so availability is undefined | Open |
| All other accounts with expenditure activity | $36,206.12 | Open |
Accounts: 300 · Available: 233,880.44
Publication #2741, data through 2026-11-18. Only accounts with expenditure activity are measured here; revenue accounts carry no expenditure availability.How this figure is computed
| Account | Description | Revised budget, not sorted | Expenditure, not sorted | Available, not sorted | Commitments, not sorted | Utilisation, not sorted | Account, not sorted | Prior year | Status |
|---|---|---|---|---|---|---|---|---|---|
| 202-3-00-90-910-0000-00-110-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $1,360,000.00 | $482,477.22 | -$108,695.13 | $986,217.91 | 35.5% | $1,360,000.00 | $1,880,890.13 | |
| 202-3-00-90-910-0000-00-133-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $10,000.00 | $372,329.84 | -$434,746.24 | $72,416.40 | 3723.3% | $10,000.00 | $16,937.24 | |
| 202-3-00-90-910-0000-00-140-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $800,000.00 | $202,703.19 | $203,593.16 | $393,703.65 | 25.3% | $800,000.00 | $1,236,174.96 | |
| 202-3-00-90-910-0000-00-122-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $400,000.00 | $179,452.75 | $195,537.25 | $25,010.00 | 44.9% | $400,000.00 | $467,098.00 | |
| 202-3-00-90-910-0000-00-131-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $300,000.00 | $82,926.38 | $146,847.10 | $70,226.52 | 27.6% | $300,000.00 | $331,172.19 | |
| 202-3-00-90-910-0000-00-134-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $230,000.00 | $24,305.00 | $174,101.00 | $31,594.00 | 10.6% | $230,000.00 | $233,660.40 | |
| 202-3-83-90-910-0109-00-000-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $0.00 | $6,321.04 | Not applicable | $0.00 | Not applicable | $0.00 | $8,252.16 | |
| 202-3-00-90-910-0000-00-100-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Contracted Construction | $0.00 | $6,081.25 | Not applicable | $0.00 | Not applicable | $0.00 | $295.26 | |
| 006-3-00-90-910-0000-00-110-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $3,372.28 | Not applicable | $35,040.00 | Not applicable | $0.00 | $360,284.66 | |
| 202-3-00-90-940-0000-00-100-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / System Planning | $19,000.00 | $1,950.76 | $17,049.24 | $0.00 | 10.3% | $19,000.00 | $19,929.38 | |
| 202-3-00-90-920-0000-00-122-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Capital Construction-In House | $5,000.00 | $1,012.06 | $3,987.94 | $0.00 | 20.2% | $5,000.00 | $5,250.03 | |
| 006-3-00-90-910-0000-00-133-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $493.41 | Not applicable | $0.00 | Not applicable | $0.00 | $22,629.58 | |
| 202-3-00-90-920-0000-00-100-486919- | Proj Plnng · Capital Improvements Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $194.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-920-0000-00-122-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $11.05 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-1-00-00-101-0000-00-000-486919- | Proj Plnng · General Fund / No Department / General Office | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-2-10-25-251-0711-01-000-486919- | Proj Plnng · General Fund / General Recreation / Community Recreation | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-2-10-25-251-0809-01-000-486919- | Proj Plnng · General Fund / General Recreation / Community Recreation | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-2-50-25-251-0912-01-000-486919- | Proj Plnng · General Fund / General Recreation / Community Recreation | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-00-00-920-0000-00-000-486919- | Proj Plnng · General Fund / No Department / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-00-80-000-0000-00-000-486919- | Proj Plnng · General Fund / Park Operations / No Division | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-00-90-920-0000-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-10-90-920-0508-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-10-90-920-0708-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-10-90-920-0711-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-10-90-920-1014-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-30-90-920-0407-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-30-90-920-0412-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-50-90-920-0306-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 001-3-50-90-920-0901-00-000-486919- | Proj Plnng · General Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-910-0000-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-910-0000-00-100-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | $4,386.25 | |
| 006-3-00-90-910-0000-00-121-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-910-0000-00-122-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | $106.56 | |
| 006-3-00-90-910-0000-00-131-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | $203,527.60 | |
| 006-3-00-90-910-0000-00-132-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-910-0000-00-134-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | $116,914.74 | |
| 006-3-00-90-910-0000-00-140-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-910-1401-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | $17,450.00 | |
| 006-3-00-90-920-0000-00-100-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-920-0000-00-110-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-920-0000-00-121-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-920-0000-00-131-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-920-0000-00-140-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-00-90-940-0000-00-100-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / System Planning | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-10-90-910-0218-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-10-90-910-0708-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-10-90-910-0711-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-10-90-920-0508-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-10-90-920-1014-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Capital Construction-In House | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| 006-3-30-90-910-0407-00-000-486919- | Proj Plnng · Enhancement Operating Fund / Planning and Engineering / Contracted Construction | $0.00 | $0.00 | Not applicable | $0.00 | Not applicable | $0.00 | Not published | |
| Total over all matching accounts | $3,185,500.00 | $1,363,630.23 | $233,880.44 | $1,639,502.36 | 42.8% | $3,185,500.00 | $5,216,547.45 | ||
How to read these figures
- Rows shown: 50 of 300 matching accounts. The totals row above is computed over all 300 — paging never changes it.
- Available budget = revised − expenditure − encumbrance − requisition, shown only when the revised budget is above zero.
- Revenue accounts show their own measures; expenditure availability is not applied to them.
- The charts summarise every account matching the filters, not only the page on screen. What a top-12 chart leaves out is labelled with its own amount, and the totals row always states the whole population.
- In the utilisation chart every matching account is counted: buckets for accounts with no published budget and for accounts whose revised budget is zero or negative are stated rather than dropped, and each bucket links to this same table filtered to that bucket.